Enbridge Berth 2A Modifications

Project Description:

The MODA Midstream Berth 2A Modifications Project consisted of procuring and installing six monopiles that will serve as new Mooring & Breasting Dolphins that will allow the client to take on large shipping vessels, as well as a loading arm platform that aligns with the reinstated breasting line. The client requested that the berth modifications substantial completion milestone be reached in a single mobilization over a 45 day duration. Substantial completion was reached in 30 days, 15 days ahead of schedule. 

The berth modification consisted of the following scopes of work and construction duration: 

– Berth 2A:  

o Substantial Completion Duration: 10/18/2021 – 11/17/2021 – 31 Calendar Days 

o Installation of Six – 84”Ø x 190’ Mooring & Breasting Dolphins w/ accompanying Jacket 

sleeves, concrete cap, quick release hooks. Breasting Dolphins received fender systems. 

o Installation of Eight – 24”Ø x 110’ batter piles for walkway installation. 

o Installation of Ten – 60”Ø x 120’ plumb piles as the Berth 2A Platform driven pile 

foundation.  

o Installation of Berth 2A Platform Weighing in at 510 Tons 

Project Images
Project Specifications
Award Date: March 30, 2021
Completion Date: January 2022
Location: Ingleside, TX