Enbridge Berth 4 & 5
Project Description:
The MODA Midstream Berth 4 & 5 Modifications Project consisted of procuring and installing 20 EA monopiles that serve as new Mooring Dolphins & Breasting dolphins that allow the client to take on large shipping vessels, as well as 2 loading arm platforms that align with the new breasting line. The client requested that each of the berth’s modifications be completed in separate mobilizations over a specific duration. Each berth consisted of the following scopes of work and durations:
- Berth 5:
- Duration: 6/15/2020 – 7/15/2020
- Installation of 4 – 96”x190’ Breasting Dolphins & 5 – 102”x190’ Mooring Dolphins w/ accompanying Jacket sleeves, concrete cap, fender & quick release hooks.
- Installation of 2 EA 60” batter piles for walkway installation.
- Berth 4:
- Duration: 8/24/2020 – 4/2/2021
- Installation of 5 – 102”x190’ breasting Dolphins & 6 – 102”x190’ Mooring Dolphins
- Installation of 16 EA 60” plumb piles for Loading Arm Platforms – 2 EA – 4S & 4N Platform
- Installation 8 – 60” batter piles for breasting dolphin platform walkways
Project Images
Project Specifications
Award Date: | December 2019 |
Completion Date: | April 2021 |
Location | Ingleside, TX |