POCCA Oil Dock 15

Project Description:

The scope of work for Construction of Oil Dock 15 generally includes: dredging, construction of a dock platform and approach way with multi-pile breasting and monopile mooring structures, fendering system, installation of shoreline sheet pile bulkhead and articulated block mat shoreline revetment. Site work improvements include a limestone parking and work area, area lighting, potable water and a firewater system. Work also includes fabrication, installation and commissioning of electrical and mechanical systems, including piping, pipe racks, electrical building and related items, as well as installation of owner-supplied marine loading arms, dock safety unit and vapor combustion unit.

Project Images
Project Specifications
Award Date: October 5, 2016
Completion Date: February 28, 2017
Location: Corpus Christi, TX