Project Description:
The scope of this competitively bid contract for the United States Coast Guard in Port Aransas, Texas was comprised of the installation and construction of their new Marine Bulkhead Facility.
This project consisted of 450 linear feet of sheet pile bulkhead, 300 linear feet of sheet pile deadman with tie back system, an all-new fuel system, electrical, and a steel boat house.
Russell Marine was required to maintain current United States Coast Guard operations throughout the entirety of the project, maintain strict emergency procedure guidelines, and ensure access to facilities and vessels at all times within a small footprint.
Project Images
Project Specifications
Award Date: | March 2021 |
Completion Date: | August 2022 |
Location: | Port Aransas, TX |